Planning Board Approves PSE&G Substation for Trent Place
Montgomery Planning Board unanimously approved PSE&G substation preliminary and final site plan. Dave Campeas chaired with members Ibad Khan, Mayor Neena Singh, Anthony Glockler, and Om Sharma voting 5-0 to accept the application for the unmanned 69/13 kV substation at 151 Trent Place.
Planning Board · Meeting of August 10, 2026
NJ MONTGOMERY — Montgomery Planning Board unanimously approved PSE&G substation preliminary and final site plan. Dave Campeas chaired with members Ibad Khan, Mayor Neena Singh, Anthony Glockler, and Om Sharma voting 5-0 to accept the application for the unmanned 69/13 kV substation at 151 Trent Place. The facility will serve approximately 6,000 customers including East Mountain Hospital and Carrier Clinic and will provide capacity for roughly 35 megawatts of solar generation.
Construction is anticipated to begin June 2027 and continue for approximately two and one-half years with completion by the end of 2029.
In the full story:
- The complete report — 362 words
Source: the Planning Board meeting of August 10, 2026, compiled from the official minutes.
Members read the rest of this story and every Montgomery meeting we cover, in full.
Become a memberAlready a member? Sign inA 30-day free trial needs a payment method. After it, your membership renews at the price shown at checkout until you cancel, which you can do anytime from your account. Subscription terms
Share this brief
Know someone in Montgomery who follows town government? Share Townbrief Montgomery: they can sign up free.